Intermodal Station Progress         
Progress is slow but continues. So far, relocating the existing utilities, finding hidden sewer lines and starting to build the new, temporary, entrance for Amtrak. As soon as the utility cutover is finished and the new entrance is finished, the real work will start with drilling new foundation.